Question: 1. A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the

1. A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or more? -0.40000 0.02275 0.34444 0.97725 4.20000

2. Which of these statements regarding time-cost tradeoffs in CPM networks is TRUE? Crashing is possible even if there are multiple critical paths. Crashing a project often reduces the length of long-duration, but noncritical, activities. Activities not on the critical path can never be on the critical path, even after crashing. The crash time always exceeds the normal time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!