Question: A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical
A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or more?
A. 0.02275
B. 0.97725
C. 4.20000
D. 0.34444
E. 0.40000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
