A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or more?

A. 0.02275

B. 0.97725

C. 4.20000

D. 0.34444

E. 0.40000