Question: 1) A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and

1) A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Show all mathematical work and explain how you reached each answer below.

Observation:

1

2

3

4

5

Task time (seconds):

82

74

80

88

76

(a) What is the actual average time for this task?

(b) What is the normal time for this task if the employee worked at a 10% faster pace than is typical for adequately trained workers?

(c) What is standard time for this task if allowances sum to 12%?

(d) If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned) work environment, and that the proper allowance was not 12% but 20%, what is the revised standard time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!