Question: 1 A Moving to another question will save this response. estion 29 (CH 11) The risk management team of a software project has decided that

1 A Moving to another question will save this
1 A Moving to another question will save this response. estion 29 (CH 11) The risk management team of a software project has decided that due to the lack of adequate talent in your company, to open als wethe part de decided to outsource it. This is not an example of which of the following a. Risk avoidance b. Risk mitigation C. Risk acceptance d. All given answers L Moving to another question will save this response. lenovo