Question: 1 A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing them will require a lot of additional
1 A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing them will require a lot of additional work to be done.
The company made a decision to book more staff and equipment from their subcontractors in order to adhere to the agreed timeline. The customer agreed to this decision.
What will most likely happen?
a The contractor's indirect costs will increase and the customer's payment for them will increase too
b The contractor's indirect costs will increase, but the customer's payment for them will not increase
c The contractor's indirect cost will not increase, but the customer's payment for them will
d Both the contractor's indirect costs and customer's payment for them will not increase
2 A project management team is evaluating the causes that might contribute to unsatisfactory performance and quality. Which of the following statements is not true?
a Normal process variation is attributable to random causes and sometimes also called "white noise".
b Special causes are easier to predict and handle than random causes (also called common causes).
c Special causes are unusual events which are difficult to foresee and often produce outliers.
d A process can be optimized to limit the bandwidth of variations due to random causes.
3 You are performing a project management audit in your company and find that most of the project plans are neither consistent nor up-to-date.
Which of the following statements is not true?
a Projects should never be executed without a valid, updated and working project management plan.
b The consistency of the project management plan is secondary because it is only the results that matter.
c A great deal of effort is required to develop and update a project plan, but the benefits include less pressure on all stakeholders and a resulting product that will satisfy the requirements.
d Poor planning and insufficient updating of project management plans are common reasons for cost and time overruns.
4 You want to perform active risk acceptance. What should you do?
a Create contingency reserves in resources, money and time.
b Develop a plan to minimize impact in case that an identified risk occurs.
c Develop a plan to minimize the probability of occurrence for identified risks.
d Make additional resources available to speed up the project.
5 When do bidder conferences normally take place?
a After the contract has been awarded to keep alternatives open.
b After submission of bid or proposal, but before contract award.
c Prior to the submission of a bid or proposal by the bidder.
d After technical meetings with bidders to discuss contract requirements.