Question: 1 A program financial accountant learns that a project is currently earning $ 1 . 1 5 for each dollar actually spent. The accountant is

1A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the
Question 24 options:
BAC.
CPI.
EV.
SV.
SPI.During which of the following processes, risks are analyzed numerically?
Question 23 options:
Perform Quantitative Risk Analysis
Plan Risk Management
Perform Qualitative Risk Analysis
Monitor Risks