Question: A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by

A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the

  • EV.

  • BAC.

  • SV.

  • SPI.

  • CPI.