Question: 1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Duration (days) Activity a. organize layout
1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Duration (days) Activity a. organize layout team 3 b. organize modification team 6 c. design personnel jobs 6 d. set machinery in place 4 7 4 e. connect utilities f. modify conveyor system g. train personnel h. finishing touches i. run test lot 543 a) Find ES, EF, LS, LF, and Slack values all activities. b) What is (are) the critical path(s)? c) What is expected project duration? d) If activity A is delayed by 1 day, what is new expected project duration? e) If activity D is delayed by 1 day, what is new expected project duration? 1 2 C a b d 3 4 e 5 4 6 h g i 7 8