Question: 1. A project is being analyzed with below activities identified. Activities A and B start on day 0. ImmediateDuration Activity Predecessors (days) a. organize layout

1. A project is being analyzed with below activities identified. Activities A and B start on day 0.

ImmediateDuration

ActivityPredecessors(days)

a. organize layout team-3

b. organize modification team-6

c. design personnel jobsa6

d. set machinery in placeb4

e. connect utilitiesc,d7

f. modify conveyor systeme4

g. train personnele5

h. finishing touchesf4

i. run test lotg3

a)Find ES, EF, LS, LF, and Slack values all activities.

b)What is (are) the critical path(s)?

c)What is expected project duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!