Question: 1) A risk management plan that includes at least one major risk, one medium risk and one acceptable risk. 2) An expense budget for the
1) A risk management plan that includes at least one major risk, one medium risk and one acceptable risk.
2) An expense budget for the activity elements included in the plan. Show details of Labor, Material and facilities rental.
*Mary is planning her wedding and develops the following preliminary information.
| Activity | Task | Immediate Predecessors | Estimated Normal Time (weeks) |
| A | Select wedding date | None | 1 |
| B | Select wedding location | None | 4 |
| C | Prepare guest list Who is attending? | A, B | 3 |
| D | Select entertainment | A | 4 |
| E | Choose catering | A, C | 3 |
| F | Wedding day | D, E | 0 |
Reference:
Computational Exercise Questions 19.2-36 on page 596
David Alan Collier; James R. Evans - Operations and Supply Chain Management, 2nd Edition (2019).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts