Question: 1. A software company created a base package that must be implemented for each customer. Which one of the following will be used to ensure
1. A software company created a base package that must be implemented for each customer. Which one of the following will be used to ensure that the new base functionally does not break existing custom features and that these changes are evaluated across all relevant versions of the product?
A.Configuration management system
B.Process improvement plan
C.Perform Integrated Change Control
D.Work authorization system
2.Ashley, a senior project manager, recently took over a project to produce a safe and effective drug from another project manager who just left the company. Ashley was
surprised to find out that there is no change control board to review, approve, or deny a change request for the project. Upon further investigation, she finds that there is no
organizational change control board to manage changes for the entire organization. What should Ashley do in this situation?
A.Carry on with the change request without a change control board.
B.Establish a Change Control Board (CCB) for her project.
C.Make all the decisions about the requested changes herself with the help of the team members.
D Ask the sponsor to approve or deny the change requests.
3.After a major milestone release, some of the key stakeholders are not happy and complain that their requirements are not met. The project manager should have involved them
in which of the following processes to ensure their approval for the release?
A.Project Management Plan Development
B.Identifying Constraints
C.Validate Scope
D.Schedule Management
4) Ashley, a senior project manager, recently took over a project to produce a safe and effective drug from another project manager who just left the company. Ashley was
surprised to find out that there was no change control board or change control process established for the project. Why is it important to have a robust change control process for
any project to be successful?
A.It will ensure that only stakeholders with significant authority can submit the change requests.
B.It will minimize the number of changes in the project.
C.It will ensure that only necessary changes are considered and implemented.
D.It will maintain the record of all changes for budget tracking purposes.