Question: 1 . ( A through K ) with the following processing times ( in hours ) :A ( 1 0 ) , B ( 7

1.(A through K) with the following processing times (in hours):A(10), B(7), C(11), D(8), E(9), F(5), G(3), H(6), I(4), J(7),K (5).A schedule with N=5 processors has finishing timeFin =19 hours. What is the total idle time for all theprocessors?(b) Explain why a schedule with N=5 processors must have finishing time Fin 15 hours.