Question: 1) Activity (A) Develop business plan [Duration (2months)] Predecessor (none) Slack Activity (B) Buy and create website [Duration (2 weeks)] Predecessor (A) Slack Activity (C)
1)
Activity (A) Develop business plan [Duration (2months)] Predecessor (none) Slack
Activity (B) Buy and create website [Duration (2 weeks)] Predecessor (A) Slack
Activity (C) Develop prod. architecture [Duration (8 months)] Predecessor (A) Slack
Activity (D) Seek investors/funding [Duration (6 months)] Predecessor (A) Slack
Activity (E) Hire additional workers [Duration (3 months)] Predecessor (D) Slack
Activity (F) Buy computers & supplies [Duration (2 weeks)] Predecessor (D) Slack
Activity (G) Rent space for office [Duration (1.5 months)] Predecessor (D) Slack
Activity (H) Move into and open office [Duration (2 weeks)] Predecessor (G) Slack
Activity (I) Develop detailed product [Duration (9 months)] Predecessor (C,E,F) Slack
Activity (J) Sell and ship 1st product [Duration (1 month)] Predecessor (B,H,I) Slack
1a) Draw an activity on node network diagram for this project. (Use months as your working units, assuming that 4 weeks = one month)
1b) Identify the critical path and how long the entire project will take. For full credit, show me why this path is critical.
1c) Complete the table by identifying the slack time for each activity. Make sure to express all of your answers using months as your unit of measure.
1d) Draw a design structure matrix for this project