Question: Activity Duration Predecessor A Develop business plan 2 months none B Buy and create website 2 weeks A C Develop prod. architecture 8 months A

Activity Duration Predecessor A Develop business plan 2 months none B Buy and create website 2 weeks A C Develop prod. architecture 8 months A D Seek investors/funding 6 months A E Hire additional workers 3 months D F Buy computers & supplies 2 weeks D G Rent space for office 1.5 months D H Move into and open office 2 weeks G 1 Develop detailed product 9 months C, E, F J Sell and ship 1st product 1 month B, H, I 2) Identify the critical path and how long the entire project will take. For full credit, explain or compare to show why this path is critical