Question: 1. Activity A is immediate predecessor for activities B, C, and D. Activity time of A is 7, B is 3, C is 6 and

1. Activity A is immediate predecessor for activities B, C, and D. Activity time of A is 7, B is 3, C is 6 and D is 6. Latest Start time of activity B is 20, C is 20 and D is 16. Writedown the Latest Start time of activity A.

2. Activities A, B, and C are immediate predecessors of Activity D. Activity time for A is 5, for B is 5, for C is 9 and for D is 11. Earliest Start time of activity A is 14, B is 15 and C is 15. Writedown the Earliest Finish time of Activity D.