Question: Activity A is immediate predecessor for activities B, C, and D. Activity time of A is 11, B is 10, C is 6 and D

Activity A is immediate predecessor for activities B, C, and D. Activity time of A is 11, B is 10, C is 6 and D is 3. Latest Start time of activity B is 18, C is 15 and D is 21. Writedown the Latest Start time of activity A.