Question: 1. Activity Preceding activity Optimistic time estimates (Weeks) Most Likely time estimates (Weeks) Pessimistic time estimates (Weeks) A - 3 5 6 B - 2

1.

Activity

Preceding activity

Optimistic time estimates (Weeks)

Most Likely time estimates (Weeks)

Pessimistic time estimates (Weeks)

A

-

3

5

6

B

-

2

4

6

C

A

4

6

7

D

B

3

5

8

E

A, C, D

5

7

10

  1. Draw an AON diagram based on the activities and their relationships given in the table. (1 mark)
  2. Determine the expected time estimates for all the activities. (1.5 marks)
  3. Find the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and Slack time for each activity of the project. (1.5 marks)
  4. Determine the total variance of the critical path. (2 marks)
  5. What is the probability that project can be completed within 20 weeks? (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!