Question: What is the estimated standard deviation in the time for activity Z ? Activity Immediate Predecessor Optimistic Time Estimates ( days ) Most Likely Time

What is the estimated standard deviation in the time for activity Z?
Activity
Immediate Predecessor
Optimistic Time
Estimates (days)
Most Likely Time
Estimates (days)
Pessimistic Time
Estimates (days)
U
_
35
50
65
V
_
28
40
52
W
U, V
26
35
44
X
V
28
40
52
Y
X
26
29
38
Z
W, Y
36
60
84
5 days
8 days
3 days
4 days
2 days