Question: 1. After developing the schedule using the critical path method, some resources were planned above available capacity. Which of the following could help solve this
1. After developing the schedule using the critical path method, some resources were planned above available capacity. Which of the following could help solve this problem?
Resource levelling
Resource soothing
Monte Carlo
Critical chain method
2. Which of the following regarding milestones is not true?
They are not work activities
Senior management may impose milestones
They are defined during the sequence activities process
They can be used as checkpoints
3. A project manager is currently documenting rules for schedule performance measurement through earned value management schedule variance (SV) and schedule performance index (SPI). Which process is the project manager working in?
Plan procurement management
Project schedule management
Develop schedule
Plan schedule management
4. In which of the following can you document activities, events, and dependencies?
Network diagram
WBS
Activity list
Sequence activities
5. After budget approval, an additional and unexpected cost item has been identified, which made the project more expensive some weeks ago. The item has meanwhile been paid by the project team, and it is expected that for the remaining duration of the project, costs will be as budgeted. In this case, which is the best formula to calculate EAC (Estimate at Completion)?
EAC = BAC CV
EAC = BAC / CPI
You cannot compute the EAC
EAC = AC + BTC / CV
6. One week after starting the development of a new electric component, you can begin technical documentation. Which of the following would you use to model such dependency?
Use start-to-start relationship with one week slack
use start-to-start relationship with one week lead
Use finish-to-start relationship with one week slack
Use start-to-start relationship with one week lag
7.The PM has just determined cost estimates and is about to move into the next planning process. What has he/she forgotten to do?
Provide the basis for estimates
Provide a cost baseline
Determine funding requirements
Provide the project CPI
8. Ambrose is a project team member responsible to assist the project manager in developing and maintaining the project schedule. He finds it difficult to develop the project schedule and uses a method that is known to him from his past experiences. The project manager notices this, and in order to ensure that the right method is used to develop the schedule, asks Ambrose to follow the:
Project Charter
Schedule Management Plan
Project Schedule
Schedule Network Diagram