Question: After developing the schedule using the critical path method, some resources were planned above available capacity. Which of the following can help solve the problem?
After developing the schedule using the critical path method, some resources were planned above available capacity. Which of the following can help solve the problem?
A. Monte Carlo B. Resource smoothing C. Resource leveling D. Critical chain method