Question: 1 . An R&D lab required 6 2 labor hours to assemble the first prototype of a new product. The second prototype required 3 7
An R&D lab required labor hours to assemble the first prototype of a new product. The second prototype required labor hours. Assuming a consistent learning rate how many hours would you expect to be required to assemble the th unit?