Question: 1- An work package can include only one or more activities. True False 2- A project that has several near-critical or critical paths is said

1- An work package can include only one or more activities.

True

False

2- A project that has several near-critical or critical paths is said to be

A)elastic or flexible and responsive to change

B) critically risky

C) supper critical project

D) duration sensitive as any delay may reduce the chance of finishing the project on schedule.

3- Which of the following activities is the best example of a project? Overseeing customer requests Producing automobiles Monitoring product quality Processing insurance claims Writing a policy manual

4-

Consider the following data for an IT project. If the Indirect cost of the project is $1000 per day, and each activity could be shorten by maximum of two days, what is the cost at the optimum project duration?

1- An work package can include only one or more activities. True5-

False 2- A project that has several near-critical or critical paths is

Based on information provided in the above table what is the peak resource demand for R1 using time constraint scheduleing (the duration must not change)?

A) 7

B) 2

C) 6

D) 4

\begin{tabular}{|l|l|l|l|l|} \hline Activity & Predecessors & Duration & Crash Cost/day (\$) & NormalDirectcost \\ \hline A & - & 12 & 1000 & 12000 \\ \hline B & A & 10 & 2200 & 13000 \\ \hline C & A & 13 & 500 & 7000 \\ \hline D & A & 8 & 1000 & 9000 \\ \hline E & D & 13 & 1000 & 13000 \\ \hline F & B,C & 6 & 500 & 8000 \\ \hline G & E,F & 11 & 1000 & 22000 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!