Question: 1 Assembly Line Balancing Question ( 1 ) The work elements, precedence requirements, and time requirements to assemble a Picture frame are shown here. Construct

1 Assembly Line Balancing
Question (1) The work elements, precedence requirements, and time requirements to assemble
a Picture frame are shown here.
Construct a precedence diagram of the process and label task times.
Set up an assembly line capable of producing 1,600 frames per 40-hour week.
Calculate the efficiency and idle time of the line.
Element Description Precedence Time (minutes)
A Attach left frame side to top of frame. -0.35
B Attach right frame side to bottom of frame. -0.35
C Attach left and right frame subassemblies. A, B 0.70
D Cut 8-inch x 10-inch glass. -0.50
E Cut 8-inch x 10-inch cardboard. -0.50
F Place glass into frame. C, D 0.20
G Place cardboard into frame. C, E, F 0.20
H Secure cardboard and glass. F, G 0.50
I Apply descriptive label to glass. D 0.1 Calculate the cycle timeQuestion (1) The work elements, precedence requirements, and time requirements to assemble
a Picture frame are shown here.
Construct a precedence diagram of the process and label task times.
Set up an assembly line capable of producing 1,600 frames per 40-hour week.
Calculate the efficiency and idle time of the line.
 1 Assembly Line Balancing Question (1) The work elements, precedence requirements,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!