Question: 1 Assembly Line Balancing Question ( 1 ) The work elements, precedence requirements, and time requirements to assemble a Picture frame are shown here. Construct
Assembly Line Balancing
Question The work elements, precedence requirements, and time requirements to assemble
a Picture frame are shown here.
Construct a precedence diagram of the process and label task times.
Set up an assembly line capable of producing frames per hour week.
Calculate the efficiency and idle time of the line.
Element Description Precedence Time minutes
A Attach left frame side to top of frame.
B Attach right frame side to bottom of frame.
C Attach left and right frame subassemblies. A B
D Cut inch x inch glass.
E Cut inch x inch cardboard.
F Place glass into frame. C D
G Place cardboard into frame. C E F
H Secure cardboard and glass. F G
I Apply descriptive label to glass. D Calculate the cycle timeQuestion The work elements, precedence requirements, and time requirements to assemble
a Picture frame are shown here.
Construct a precedence diagram of the process and label task times.
Set up an assembly line capable of producing frames per hour week.
Calculate the efficiency and idle time of the line.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock