Question: 1 Assembly Line Balancing Question ( 1 ) The work elements, precedence requirements, and time requirements to assemble a Picture frame are shown here. Construct

1 Assembly Line Balancing
Question (1) The work elements, precedence requirements, and time requirements to assemble a Picture frame are shown here.
Construct a precedence diagram of the process and label task times.
Set up an assembly line capable of producing 1.600 frames per 40-hour week.
Calculate the efficiency and idle time of the line.
\table[[Element,Description,Precedence,Time (minutes)],[A,Attach left frame side to top of frame.,-,0.35],[B,Attach right frame side to bottom of frame.,-,0.35],[C,Attach left and right frame subassemblies.,A. B,0.70],[D,Cut 8-inch x 10-inch glass.,-,0.50],[E,Cut 8-inch x 10-inch cardboard.,-,0.50],[F,Place glass into frame.,C. D,0.20],[G,Place cardboard into frame.,C. E, F,0.20],[H,Secure cardboard and glass.,F, G,0.50],[I,Apply descriptive label to glass.,D,0.10]]
 1 Assembly Line Balancing Question (1) The work elements, precedence requirements,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!