Question: 1. Assign the system development activities to the awarded contract performance cycle (illustrated in figure below) by placing the correct letter in the blank for

1. Assign the system development activities to the awarded contract performance cycle (illustrated in figure below) by placing the correct letter in the blank for each activity Software code, bulkheads, manufacturing instruction Understand Stakeholders' requirement, develop system concept Develop System Validation Plan Develop System Concept Validation Plan Develop System Performance Specification Evolve "Design-To" specification into "Build-to" Documentation Expand Performance Specs into CI "Design-to" Specifications Develop Verification Plan Inspect "Build-to" Documentation Integrate System and Perform System Verification to Performance Specs Assemble Cis and Performance CI verification to CI "Design-to" Specs Demonstrate and Validate System to Stakeholders Validation Plan