1. Assume that your project has started to slip dramatically. Lets further assume that the project deadline is fixed and can't change. Your project currently has one developer working on module of code with 21 day duration on the critical path. You are desperate to shorten this timeframe and you are considering adding a second resource to this activity but, the resource does not have all the right skills and he might work five days just to reduce the overall time by two days. From an economic perspective is this a good move? Why?