1. Assume the following activities for a project along with their estimated durations and predecessors. Activity...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
1. Assume the following activities for a project along with their estimated durations and predecessors. Activity a) b) A B C D E F G H 1 J Predecessor None A A A A B,C D,E,F E F G,H,I Optimistic Estimates (Days) a 2 4 3 2 4 2 31 in 5 2 Most Likely Pessimistic Estimates Estimates (Days) b 2 5 2 3 3 4 2 NN 2 3 1 (Days) C 4 6 5 6 2 6 3 5 8 4 Expected Duration Calculate the expected duration for each activity. Demonstrate the calculation of determining the critical path and identify the project duration time. 1. Assume the following activities for a project along with their estimated durations and predecessors. Activity a) b) A B C D E F G H 1 J Predecessor None A A A A B,C D,E,F E F G,H,I Optimistic Estimates (Days) a 2 4 3 2 4 2 31 in 5 2 Most Likely Pessimistic Estimates Estimates (Days) b 2 5 2 3 3 4 2 NN 2 3 1 (Days) C 4 6 5 6 2 6 3 5 8 4 Expected Duration Calculate the expected duration for each activity. Demonstrate the calculation of determining the critical path and identify the project duration time. 1. Assume the following activities for a project along with their estimated durations and predecessors. Activity a) b) A B C D E F G H 1 J Predecessor None A A A A B,C D,E,F E F G,H,I Optimistic Estimates (Days) a 2 4 3 2 4 2 31 in 5 2 Most Likely Pessimistic Estimates Estimates (Days) b 2 5 2 3 3 4 2 NN 2 3 1 (Days) C 4 6 5 6 2 6 3 5 8 4 Expected Duration Calculate the expected duration for each activity. Demonstrate the calculation of determining the critical path and identify the project duration time. 1. Assume the following activities for a project along with their estimated durations and predecessors. Activity a) b) A B C D E F G H 1 J Predecessor None A A A A B,C D,E,F E F G,H,I Optimistic Estimates (Days) a 2 4 3 2 4 2 31 in 5 2 Most Likely Pessimistic Estimates Estimates (Days) b 2 5 2 3 3 4 2 NN 2 3 1 (Days) C 4 6 5 6 2 6 3 5 8 4 Expected Duration Calculate the expected duration for each activity. Demonstrate the calculation of determining the critical path and identify the project duration time.
Expert Answer:
Answer rating: 100% (QA)
To determine the expected duration of each activity you can use the formula below to find Excepted D... View the full answer
Related Book For
Managerial Decision Modeling With Spreadsheets
ISBN: 9780136115830
3rd Edition
Authors: Nagraj Balakrishnan, Barry Render, Jr. Ralph M. Stair
Posted Date:
Students also viewed these programming questions
-
1. Consider the graph below: a b j i d 9 f (a) Starting with the matching M = {{c,d}}, iteratively extend M until a maximum matching is found. Do this by finding augmenting paths at each iteration....
-
Coase Theorem: There is 1 firm (polluter) and 1 household (pollution victim). The firm incurs all abatement costs, and the household incurs all damages from pollution. Society faces a choice between...
-
Data for Hermann Corporation are shown below: Selling price Variable expenses Contribution margin Percent Per Unit of Sales $ 130 78 100% 60 $ 52 40% Fixed expenses are $86,000 per month and the...
-
(a) lim f(x) X-C+ 5. y 7. Y 9. 2 IT - Limits and Continuity In Exercises 5-10, use the graph to determine each limit, and discuss the continuity of the function. -3+ (4,3), + + 1/2 3 4 (3, 1) (b) lim...
-
1. What type of team does the new CIO have? What do you see as the key problem with the team? 2. How do you think that the team evolved to this low level of cooperation and cohesiveness? 3. What...
-
During the first month of operations ended July 31, 2016, YoSan Inc. manufactured 2,400 flat panel televisions, of which 2,000 were sold. Operating data for the month are summarized as follows: Sales...
-
Compute the point estimates b0 and b1. Exercises 610 refer to the following data set: x 25 13 16 19 29 19 16 30 y 40 20 33 30 50 37 34 37
-
Arm BCD is connected by pins to crank AB at B and to a collar at C. Neglecting the effect of friction, determine the couple M required to hold the system in equilibrium when θ = 0. -200mm---240...
-
The dean of the School of Fine Arts is trying to decide whether to purchase a copy machine to place in the lobby of the building. The machine would add to student convenience, but the dean feels...
-
Two-dimensional dynamics often involves solving for two unknown quantities in two separate equations describing the total force. The block in (Figure 1) has a mass m = 10kg and is being pulled by a...
-
Emily bought 200 shares of ABC Co. at $29.00 per share with a 60% margin. Suppose you hold the stock for one year, and interest costs over the holding period will be $80. Ignoring commissions, what...
-
How do longitudinal studies and network analysis techniques contribute to our understanding of the temporal dynamics of group cohesion, shedding light on the factors that contribute to its emergence,...
-
Find the time (in min) required for an object to cool from 300F to 260F by evaluating the following where t is time in minutes. (Round your answer to four decimal places.) 300 10 1 t = dT In(2) T-100...
-
At x = 20, you guarantee Select an answer Question 8 2 Find the critical value(s) of f(x) = 5x - x. Separate multiple answers with a comma. f(x) has critical values at x = Question 9 Find the absolute
-
You are given the following information. What is the arbitrage profit if you have 1,000,000 to use? ( = British Pound; = Euro; SEK - Swedish Krona) Bid Ask S(/SEK) 0.0996 0.0999 S(/) 0.8646 0.8656...
-
= (c) Recall e 2.71828... is Euler's constant and e is the exponential function. Since e > 2, you may assume that. lim = . Show that e xxx2 ex lim = . xxx Hint: you may use the result of part (b) and...
-
an inhomogenous 12-inch ruler by 13 massive particles connected through 1-inch massless rods. Since the ruler is not uniform, the particles must have different masses. Assuming that the ruler mass is...
-
Linda Lopez opened a beauty studio, Lindas Salon, on January 2, 2011. The salon also sells beauty supplies. In January 2012, Lopez realized she had never filed any tax reports for her business and...
-
A group of medical professionals is considering constructing a private clinic. If patient demand for the clinic is high, the physicians could realize a net profit of $100,000. If the demand is low,...
-
LeBron Woods is responsible for developing a leadership training program for his organization. The following table describes the relationships between the activities that need to be completed. (a)...
-
The farmer in Problem 3-25 has an opportunity to take over the neighboring 80-acre farm. If he acquires this farm, he will be able to increase the amounts of time available to 1,600 hours for...
-
Air passes through a normal shock in a supersonic wind tunnel. Upstream conditions are \(M_{1}=1.8, T_{1}=270 \mathrm{~K}\), and \(p_{1}=\) \(10.0 \mathrm{kPa}\) absolute. Downstream conditions are...
-
A Boeing 747 cruises at \(M=0.87\) at an altitude of \(13 \mathrm{~km}\) on a standard day. A window in the cockpit is located where the external flow Mach number is 0.2 relative to the plane...
-
Air flows isentropically through a converging nozzle into a receiver where the pressure is \(250 \mathrm{kPa}\) absolute. If the pressure is \(350 \mathrm{kPa}\) absolute and the speed is \(150...
Advances In Modern Tourism Research Economic Perspectives 1st Edition - ISBN: 379082528X - Free Book
Study smarter with the SolutionInn App