Question: LeBron Woods is responsible for developing a leadership training program for his organization. The following table describes the relationships between the activities that need to
.png)
(a) Determine the expected times and variances for each activity.
(b) Construct a project network for this problem.
(c) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the critical path and project completion time.
(d) What is the probability that the project will be finished in less than 49 days?
(e) What is the probability that the project will need at least 54 days?
DAY IMMEDIAT ACTIVITYb 3 714 5 10 15 3 5 10 5 12 13 A, B 2 514 5 8 11 6 10 14 F, H G,I 4 7 10
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
718-M-S-L-P (1179).xlsx
300 KBs Excel File