Question: LeBron Woods is responsible for developing a leadership training program for his organization. The following table describes the relationships between the activities that need to

LeBron Woods is responsible for developing a leadership training program for his organization. The following table describes the relationships between the activities that need to be completed.
LeBron Woods is responsible for developing a leadership training program

(a) Determine the expected times and variances for each activity.
(b) Construct a project network for this problem.
(c) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the critical path and project completion time.
(d) What is the probability that the project will be finished in less than 49 days?
(e) What is the probability that the project will need at least 54 days?

DAY IMMEDIAT ACTIVITYb 3 714 5 10 15 3 5 10 5 12 13 A, B 2 514 5 8 11 6 10 14 F, H G,I 4 7 10

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

718-M-S-L-P (1179).xlsx

300 KBs Excel File

Students Have Also Explored These Related Statistics Questions!