Question: 1. Assume the following information: Hours Queue time 39 Wait time 24 Process time 2 Move time 2 Inspection time 4 The delivery cycle time

1. Assume the following information:

Hours
Queue time 39
Wait time 24
Process time 2
Move time 2
Inspection time 4

The delivery cycle time is:

2. Assume the following information:

Hours
Queue time 32
Wait time ?
Process time 2
Move time 2
Inspection time ?

If the delivery cycle time is 68 hours and the manufacturing cycle efficiency (MCE) is 0.05, then the wait time is closest to:

3. Assume the following information:

Actual run time this week 4,500 minutes
Machine time available this week 5,000 minutes
Actual run rate this week 3.6 units per minute
Ideal run rate 5.4 units per minute
Defect-free output this week 15,000 units
Total output this week (including defects) 16,200 units

The efficiency rate is closest to:

4. Assume the following information:

Actual run time this week 4,500 minutes
Machine time available this week 5,000 minutes
Actual run rate this week 3.6 units per minute
Ideal run rate 4.0 units per minute
Defect-free output this week 14,000 units
Total output this week (including defects) 16,200 units

The quality rate is closest to:

5. Assume the following information:

Actual run time this week 4,500 minutes
Machine time available this week 5,000 minutes
Actual run rate this week 3.6 units per minute
Ideal run rate 4.0 units per minute
Defect-free output this week 12,800 units
Total output this week (including defects) 16,200 units

The overall equipment effectiveness (OEE) is closest to:

Note: Do not round your intermediate calculations.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!