Question: 1. Assume the following information: Hours Queue time 39 Wait time 24 Process time 2 Move time 2 Inspection time 4 The delivery cycle time
1. Assume the following information:
| Hours | |
|---|---|
| Queue time | 39 |
| Wait time | 24 |
| Process time | 2 |
| Move time | 2 |
| Inspection time | 4 |
The delivery cycle time is:
2. Assume the following information:
| Hours | |
|---|---|
| Queue time | 32 |
| Wait time | ? |
| Process time | 2 |
| Move time | 2 |
| Inspection time | ? |
If the delivery cycle time is 68 hours and the manufacturing cycle efficiency (MCE) is 0.05, then the wait time is closest to:
3. Assume the following information:
| Actual run time this week | 4,500 | minutes |
|---|---|---|
| Machine time available this week | 5,000 | minutes |
| Actual run rate this week | 3.6 | units per minute |
| Ideal run rate | 5.4 | units per minute |
| Defect-free output this week | 15,000 | units |
| Total output this week (including defects) | 16,200 | units |
The efficiency rate is closest to:
4. Assume the following information:
| Actual run time this week | 4,500 | minutes |
|---|---|---|
| Machine time available this week | 5,000 | minutes |
| Actual run rate this week | 3.6 | units per minute |
| Ideal run rate | 4.0 | units per minute |
| Defect-free output this week | 14,000 | units |
| Total output this week (including defects) | 16,200 | units |
The quality rate is closest to:
5. Assume the following information:
| Actual run time this week | 4,500 | minutes |
|---|---|---|
| Machine time available this week | 5,000 | minutes |
| Actual run rate this week | 3.6 | units per minute |
| Ideal run rate | 4.0 | units per minute |
| Defect-free output this week | 12,800 | units |
| Total output this week (including defects) | 16,200 | units |
The overall equipment effectiveness (OEE) is closest to:
Note: Do not round your intermediate calculations.