Question: 33) Hours Queue time 29 Wait time 24 Process time 2 Move time 2 Inspection time 4 The throughput time (manufacturing cycle time) is: Group

33)

Hours
Queue time 29
Wait time 24
Process time 2
Move time 2
Inspection time 4

The throughput time (manufacturing cycle time) is:

Group of answer choices

37 hours.

61 hours.

25 hours.

59 hours.

34)

Actual run time this week 4,510 minutes
Machine time available this week 5,000 minutes
Actual run rate this week 3.6 units per minute
Ideal run rate 4.0 units per minute
Defect-free output this week 15,000 units
Total output this week (including defects) 16,236 units

What is the quality loss in units?