Question: 33) Hours Queue time 29 Wait time 24 Process time 2 Move time 2 Inspection time 4 The throughput time (manufacturing cycle time) is: Group
33)
| Hours | |
| Queue time | 29 |
| Wait time | 24 |
| Process time | 2 |
| Move time | 2 |
| Inspection time | 4 |
The throughput time (manufacturing cycle time) is:
Group of answer choices
37 hours.
61 hours.
25 hours.
59 hours.
34)
| Actual run time this week | 4,510 | minutes |
| Machine time available this week | 5,000 | minutes |
| Actual run rate this week | 3.6 | units per minute |
| Ideal run rate | 4.0 | units per minute |
| Defect-free output this week | 15,000 | units |
| Total output this week (including defects) | 16,236 | units |
What is the quality loss in units?