Question: 1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this

1) Based on the given information regarding the activities for the project, the project length= ___ weeks.

2) The total cost required for completing this project on normal time= $____

3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___.

4) The cost of the project based on the first activity selected for crashing will increase by $___.

5) The maximum weeks by which the project can be reduced by crashing= ___ weeks.

6) Total cost of crashing the project to minimum (or maximum weeks possible)= $____1) Based on the given information regarding the

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Time (weeks) Activity A B AWO W NA 0 Crash Time (weeks) 3 1 3 4 3 Normal Cost $2,200 $2,100 $500 $2,500 $1,000 $3,000 $1,400 8 NN WWW Total Cost with Immediate Crashing Predecessor(s) $2,800 $2,900 $500 $2,800 $1,300 B $4,400 C $1,900 D, E a) Based on the given information regarding the activities for the project, the project length = 0 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!