Question: 1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this
1) Based on the given information regarding the activities for the project, the project length= ___ weeks.
2) The total cost required for completing this project on normal time= $____
3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___.
4) The cost of the project based on the first activity selected for crashing will increase by $___.
5) The maximum weeks by which the project can be reduced by crashing= ___ weeks.
6) Total cost of crashing the project to minimum (or maximum weeks possible)= $____
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
