Question: 1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical Path (CP), the amount of

1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical

Path (CP), the amount of slack and whether the task is a milestone.

Task Predecessors Duration CP (Yes/No)? Slack (Amount)? Milestone?

PROJECT 2

A2 - 1

B2 A2 2

C2 A2 2

D2 B2, C2 3

E2 D2 2

F2 D2 3

G2 E2,F2 2

2. Draw a PERT (Network) chart for PROJECT 2.

3. Draw a GANTT chart for PROJECT 2.

4. Schedule PROJECT 2 on a 5-day work week, indicating the tasks and slack available.