Question: 1. Company management thinks optimistically the task can be done in 10 weeks and, at the outside in 12 weeks. However, the most likely time

1. Company management thinks optimistically the

1. Company management thinks optimistically the task can be done in 10 weeks and, at the outside in 12 weeks. However, the most likely time will be 15 weeks. What is a reasonable duration for planning (3-point estimate and PERT)? (5 points)