Question: 1. Complete the table (Table2) below don't forget to explain the calculation method: the project baseline schedule is fixed to 5 months. Each phase is
1. Complete the table (Table2) below don't forget to explain the calculation method: the project baseline schedule is fixed to 5 months. Each phase is planned to be achieved in one month. And each month cost planned is fixed to 3000SAR - The project P consists in developing software in 5 phases (each phase is estimated in plan showed in table 1)