Question: 1. Compute EAC when cost performance is negative and schedule dates must be met: EAC = AC [(BAC - EV) / (CPI SPI)] 2. Compute
1. Compute EAC when cost performance is negative and schedule dates must be met: EAC = AC [(BAC - EV) / (CPI SPI)] 2. Compute EAC using actual costs to date and assuming ETC uses budgeted rate: EAC = AC (BAC - EV) 3. Interpret the results of the EAC in a. 4. Interpret the results of the EAC in b. Part 3 1. EAC becomes Cumulative AC at project completion. 2. Cumulative EV can be greater than BAC at project completion. 3. EAC can be smaller than BAC at project completion. 4. ETC can be greater than 0 at project completion
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
