Question: The Program Manager doubts your numbers. In particular, he does not believe your EAC number and requests that you calculate the EAC NOT assuming future

The Program Manager doubts your numbers. In particular, he does not believe your EAC number and requests that you calculate the EAC NOT assuming future performance will behave like past performance.

  1. Compute EAC when cost performance is negative and schedule dates must be met: EAC = AC + [(BAC - EV) / (CPI SPI)]
  2. Compute EAC using actual costs to date and assuming ETC uses budgeted rate: EAC = AC + (BAC - EV)
  3. Interpret the results of the EAC in a.
  4. Interpret the results of the EAC in b.

Based on items a-d above, what do you think the Program Manager will request from you regarding the bottom-up EAC?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!