Question: 1. Compute Earliest Due Date Calculations (including average flow time, average lateness and average tardiness and Shortest Processing Time Calculations including the above mentioned items
1. Compute Earliest Due Date Calculations (including average flow time, average lateness and average tardiness and Shortest Processing Time Calculations including the above mentioned items for the following jobs.
Job # Processing Time Due Date
1 14 20
2 8 23
3 10 12
4 6 26
5 4 14