Question: 1 Consider the below table. Part X routing is machine A,B, then C, with annual production target of 165000 parts. Part Y has an annual

1 Consider the below table. Part X routing is machine A,B, then C, with annual production target of 165000 parts. Part Y has an annual target volume of 180000 parts and it's routing is machine B,A, then C. The setup time for part X is 40 minutes and 25 minutes for part Y per week. There are 36 hours of available production time per week and the company operates 45 weeks per year
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts