Question: 3.1 Consider the table below. Part X routing is machine A,B, then C, with annual production target of 130000 parts. Part Y has an annual

3.1 Consider the table below. Part X routing is

3.1 Consider the table below. Part X routing is machine A,B, then C, with annual production target of 130000 parts. Part Y has an annual target volume of 180000 parts and it's routing is machine B,A, then C. The setup time for part X is 30 minutes and 25 minutes for part Y. 3.1.1 Calculate the Machine Fractions for machines A,B, and C to produce parts X and Y. (20) [20]