Question: 1. Consider the following data for a project to install a new server at the Northland Pines High School. a. Druw the network diagram. b.

1. Consider the following data for a project to
1. Consider the following data for a project to install a new server at the Northland Pines High School. a. Druw the network diagram. b. Calculate the critical path for this project. Activity Activity Time (days) 2 Immediate Predecessor(s) B 4 5 D 2 B E 1 B F 8 B, C G 3 DE H 5 F 1 4 F J 7 GHI