Question: Please Help Developing the Project Schedule 1. Consider the following data for a project to install a new server at the Northland Pines High School.

Please Help

Please Help Developing the Project Schedule 1.

Developing the Project Schedule 1. Consider the following data for a project to install a new server at the Northland Pines High School. Activity Activity Time (days) Immediate Predecessor(s) A 2 B 4. A C 5 A D 2 B. E 1 B F 8 B, C G 3 D, E 3. H 5 F 1 4 F. A J 7 G, H, I a. Draw the network diagram. b. Calculate the critical path for this project. C. How much slack is in each of the activities G, H, and I? following information is known about a proiect to