#1) Consider the following project network data.

#1) Consider the following project network data. ACTIVITY PREDECESSORS A B D A E A F A G B, D H C, G I B, D J E, H K I L I M E, H, F N E, H, F O M, I P J, L, O a) Draw the AON project network. b) Calculate its critical path and its length. c) Calculate ES, LS, EF, and LF for each activity in the project. d) Calculate TS and FS. DURATION 5 3 6 8 11 3 16 9 14 7 9 12 15 10 18 2