Question: 1. Construct a network diagram using CPM method (AON). Find expected project duration, all possible path with path length, Slack time. (10). Creat an End

1. Construct a network diagram using CPM method

1. Construct a network diagram using CPM method (AON). Find expected project duration, all possible path with path length, Slack time. (10). Creat an End node. All the open node will be ended to end note. Activity Predecessor(s) Fixed Duration (days) A B D E F G H I J K L M A A B D E, H B G G J G, K F, I, L 4 8 4 5 4 2 12 2 4 6 4 7 2