Question: 1 . construct a PERT network from the image, ( make sure you have the correct network before proceeding to the next sections ) 2

1.construct a PERT network from the image,(make sure you have the correct network before proceeding to the next sections)
2.by using ES, EF, LF, LS,find the slack of each activity and the critical path
3.find the completion time and the standard deviation for the project - round off the standard deviation to the nearest hundredth: two decimal places
4.what is the completion time at 99% confidence level
5.what is the likelihood of this project being completed in more than 14 days
6.between 11 and 13 days?
 1.construct a PERT network from the image,(make sure you have the