Question: 1. Construct a product structure tree (i.e., a BOM chart). Student Name: Student Number: Question Maximum Mark Mark Obtained 4 2 3 4 4 5
1. Construct a product structure tree (i.e., a BOM chart).

Student Name: Student Number: Question Maximum Mark Mark Obtained 4 2 3 4 4 5 4 6 4 7 4 com Total 28 A company produces an end item 'F', which is composed of three subassemblies: 2 units of A, 2 units of B, and 3 units of C. A is made of 1 M and 3 Ns; B is assembled using 2 Ps and 2 Qs; and C is made of 1 X and 3 Y's. On-hand inventories are 128 As and 360 Ns. Scheduled receipts are 200 Ns at the start of week 2. Lead times are one week for all subassemblies and two weeks for all components. Final assembly of F requires one week