Question: 1. Construct an AON network diagram from the data given 2. Construct an AOA network diagram from the data given 3. Draw Gantt Chart
1. Construct an AON network diagram from the data given 2. Construct an AOA network diagram from the data given 3. Draw Gantt Chart for the data given and state what is the total duration needed to finish this project. Activity A B C D E F G H I J K L M N Immediate Predecessor B . A B C, D C, D E F, G, H F, G, H 1 J, K Duration (Mon) 3 4 6 3 9 1 4 5 4 3 6 3 6 9 63 nd Sh e PDF