Question: The following represent activities in a major construction project. Draw the network to represent this project. Activity ......................................... Immediate Predecessor A ..................................................................- B ..................................................................- C
Activity ......................................... Immediate Predecessor
A ..................................................................-
B ..................................................................-
C ..................................................................A
D ..................................................................B
E ..................................................................B
F ...............................................................C, E
G..................................................................D
H ..............................................................F, G
Step by Step Solution
3.45 Rating (164 Votes )
There are 3 Steps involved in it
St... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1132-B-M-L-O-M(6166).docx
120 KBs Word File