Question: 1. Create a task schedule for the following datathat starts Dec 01 2020 using GanttProject. Assume that one can work 7 days a week and
1. Create a task schedule for the following datathat starts Dec 01 2020 using GanttProject. Assume that one can work 7 days a week and 30 days a month:
| Code | Description of Activity | Immediate Precedence | Duration (days) |
| 1 | Strategic plan phase |
| 30 |
| 2 | Team formation | Finish with 3 | 40 |
| 3 | Master facility plan | Finish with 1 | 100 |
| 4 | Space programming | Finish with 3 | 60 |
2. Show a Gantt chart for the schedule. Make sure that the chart shows the time scale on quarterly basis. Make sure that the chart shows the critical path.
3. Create the chart and copy the chart into a word document.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
