Question: 1. Create a task schedule for the following datathat starts Dec 01 2020 using GanttProject. Assume that one can work 7 days a week and

1. Create a task schedule for the following datathat starts Dec 01 2020 using GanttProject. Assume that one can work 7 days a week and 30 days a month:

Code

Description of Activity

Immediate Precedence

Duration (days)

1

Strategic plan phase

30

2

Team formation

Finish with 3

40

3

Master facility plan

Finish with 1

100

4

Space programming

Finish with 3

60

2. Show a Gantt chart for the schedule. Make sure that the chart shows the time scale on quarterly basis. Make sure that the chart shows the critical path.

3. Create the chart and copy the chart into a word document.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!