Question: 1. Create a task schedule for the following datathat starts Dec 01 2020 using GanttProject. Assume that one can work 7 days a week and
1. Create a task schedule for the following datathat starts Dec 01 2020 using GanttProject. Assume that one can work 7 days a week and 30 days a month:
| Code | Description of Activity |
Immediate Precedence | Duration (days) |
|---|---|---|---|
| 1 | Strategic plan phase | 30 | |
| 2 | Team formation | After 3 | 40 |
| 3 | Master facility plan | After 1 | 100 |
| 4 | Space programming | After 3 | 60 |
2. Show a Gantt chart for the schedule. Make sure that the chart shows the time scale on quarterly basis. Make sure that the chart shows the critical path.
3. Create the chart and copy the chart into a word document (do not provide your project management files)
( I have already placed the information in project biz the only help I actually need in question 2. I do not know how to put the chart as a time scale on quarterly basis and showing the critical path on Ganttproject. Can someone please help me and show me what this was supposed to look in Gantt project.