Question: 1 ) Create two network diagrams based on the immediate predecessor charts. Note the critical path in each. 2 ) Conduct a forward and backward

1) Create two network diagrams based on the immediate
predecessor charts. Note the critical path in each.
2) Conduct a forward and backward pass for each network.
Calculate float and use the format pictured in the corner.
Activity Immediate Predecessor Duration
A
B
C
D
E
F
none
A
none
none
D
B, C, E
4
2
1
3
6
3
Activity Immediate Predecessor Duration
A
B
C
D
E
F
G
none
none
A
B
B
D
E
6
3
9
5
4
2

Step by Step Solution